Draw the Gantt charts pertaining to each of the Work Breakdown Structures for the Mechanical, Communication / IT and Electrical scope of work components as per Tables 5, 6 and 7 respectively.

Task 1. Draw the Gantt charts pertaining to each of the Work Breakdown Structures for the Mechanical,
Communication / IT and Electrical scope of work components as per Tables 5, 6 and 7 respectively.
(Note: The Gantt charts can be hand drawn but no free hand drawings are acceptable as this is a
formal report. All charts are to be clearly labelled showing total time duration in weeks. ) Each
Gantt chart drawn is to fit to the size of an A4 sheet of paper.
[24 Marks]
Task 2. Draw an AOA diagram for the of the Electrical Engineering scope of works, starting from and
including activity “AE” up to and including activity “RE”. Refer to Table 7. [10 Marks]
a. Find and state the critical path and determine its duration in weeks. [2 Marks]
b. State by how many weeks the installation of the interruptible power supply equipment
in the main switch rooms(s) can be delayed by, without affecting the completion
time of the overall Electrical Engineering component of the project. [2Marks]
c. State by how many weeks can the upgrade the 66kV substation at Perth airport
docking station be delayed by, without affecting the completion time of the overall
Electrical Engineering component of the project. [2 Marks]
d. State by how many weeks the installation of the lightning and surge protection equipment
be delayed by, without affecting the completion time of the overall Electrical
Engineering component of the project. [2 Marks]
e. Similarly, by how many weeks could the installation of all landing pad lights as per CASA
requirements be delayed by, without affecting the overall Electrical component project?

find the cost of your paper

Critical analysis of Change4Life Campaign

Use Subheadings– but do not use more subheadings than listed below Introduction ● Signpost reader to the contents of your essay Campaign Overview ● Identify the campaign you are focusing….

position in the Apple Valley School district-describes the work of two learning theorists and how you might apply the work of each theorist to the position you are seekin

You are applying for a position in the Apple Valley School district and know that there are several other applicants vying for the position. The district prides itself on employing….

Novel CoronaVirus – COVID-19

-Who is more Susceptible to Corona virus focus on the elderly and how it affect the elderly. -Why the elderly are at the higher risk? – How and why it….